What Is a Pre-Startup Safety Review (PSSR)?

What Is a Pre-Startup Safety Review (PSSR)?

Key takeaways
  • A PSSR confirms that a new or modified facility is safe to start.
  • It checks construction against design, procedures, training and HAZOP closure.
  • No hydrocarbons or hazardous chemicals should be introduced before PSSR sign-off.

What Is a Pre-Startup Safety Review (PSSR)?

A pre-startup safety review (PSSR) is the final safety gate before hazardous materials enter a new or modified plant. It is a core element of process safety management in chemical, petrochemical, fertilizer and gas facilities.

Why the PSSR Matters

Most serious incidents happen during non-routine operations, especially start-up. The PSSR reduces this risk by confirming that equipment, procedures and people are ready at the same time.

What a PSSR Checks

  • Construction and equipment are built according to design specifications
  • Safety, operating, maintenance and emergency procedures are in place
  • Process hazard analysis (such as HAZOP) recommendations are resolved
  • Operators and maintenance staff are trained on the new system
  • Relief valves, trips and fire protection systems are tested
  • Management of change (MOC) records are complete

PSSR for Modifications and Restarts

A PSSR is not only for new plants. Any change handled through management of change, such as a new bypass line, a replaced control valve with different characteristics, or a new chemical, should go through a PSSR scaled to the size of the change. After a long shutdown or turnaround, a restart PSSR confirms that blinds are removed, systems are reinstated and safety devices are back in service.

Scaling the review is important. A small change may need a short checklist signed by two people, while a new process unit needs a full multidisciplinary team, several field walkdowns and formal sign-off by plant management.

Practical Tips for an Effective PSSR

  • Start PSSR planning months before mechanical completion, not the week before start-up
  • Use a standard checklist but adapt it to the specific unit
  • Walk the field, not only the documents
  • Record evidence such as photos, test certificates and training records
  • Make the final sign-off by a named, accountable manager

Who Performs the PSSR?

A PSSR team usually includes operations, process engineering, maintenance, instrumentation and HSE. For large projects, an independent reviewer with commissioning experience adds real value because they can spot gaps the project team may overlook.

Frequently Asked Questions

When is a PSSR required?

A PSSR is required before starting up a new facility, and before restarting after a modification that changes process safety information.

Is a PSSR the same as a punch list?

No. A punch list records incomplete or defective work. The PSSR uses the punch list as an input but also reviews procedures, training and safety systems.

Can a plant start with open PSSR items?

Only non-critical items may remain open, and only with a documented risk assessment and approval. Safety-critical items must be closed first.

Can Grow Gas lead a PSSR?

Yes. Grow Gas supports owners during construction and commissioning with PSSR, punch listing and start-up support.

Conclusion

Whether you are planning a new project or improving an existing plant, getting these details right protects people, assets and production. Contact Grow Gas at info@growgas.com to discuss how our engineering and operations team can support your plant.